P26 · I.01(b) · N.01(b) · Project indexes · Economy · CAPEX stage-gate

Final Investment Decision — FID

Stage-gate playbook, FID package contents, LSE appraisal (NPV / IRR / payback / ARR), debiasing protocols and governance checklists.

François Dorléans · LSE MBA Essentials (Feb–Apr 2023, cert. 342406) · 11 September 2026 · partner comments locked

Decision Gates DG0 to DG6 — FID is DG3
DG0 → DG6. FID is DG3 — the irrevocable capital commitment, not the end of the path.

Partner review (protected): each section has a #tag. Comments blocked for the public until ?role=partner.

LSE golden rule before opening the file

A long-term investment decision must maximise shareholder wealth. Judge cash flows, not accounting profit. NPV is the most accurate method because it incorporates the time value of money. Study costs already spent are a sunk cost: they never justify a bad FID.

1. Purpose, audience and how to use this brief

1.1 What this brief is not

1.2 How to use it

2. What FID is — and why it changes everything

2.1 Before / at / after FID

Before FID At FID After FID
Nature of spendStudies, options, FEEDCapex commitment + launch opexExecute, commission, operate
Typical cost uncertainty±50%, then ±30%, then ±10–15%Commitment-class estimateControl vs baseline
Governance questionShould we keep studying?Do we commit the capital?Are we delivering the promised value?
Possible outcomeGo / Recycle / KillApprove / Defer / RejectChange control, lookback
Dominant biasOverconfidence, champion biasSunk-cost, confirmationPlanning fallacy realised

Table 1 — FID as a change of spending regime and governance regime.

2.2 The three committee outcomes

LSE discipline — sunk-cost fallacy (Module 8)

3. LSE MBA Essentials — what belongs inside a FID

3.1 Modules used

3.2 The four appraisal methods (LSE Module 6 Unit 4)

3.3 What LSE adds beyond the formulae

4. Stage-gate architecture to FID

Decision Gates DG0 Identify through DG6 Operate
Project image — Before FID you buy information; after FID you buy reality. DG3 = FID.

4.1 Language mapping

This brief Oil & gas / IPA Infra / utilities PMI (approx.) Typical cost uncertainty
G0 IdentifyFEL-1 AppraiseOpportunity / need caseInitiating±50% (Class 5)
G1 SelectFEL-2 SelectPre-feasibility / optionsPlanning early±30% (Class 4)
G2 DefineFEL-3 Define / FEEDFeasibility / detailed designPlanning late±10–15% (Class 3)
G3 FIDFIDFinancial close / sanctionEnd of PlanningCommitment baseline
ExecuteExecuteConstructionExecutingEAC control

Table 3 — FEL / infrastructure / PMI translation. Adapt the labels to your committee jargon, not the logic.

4.2 Economics of information

5. Gate 0 — Identify / Appraise / FEL-1

5.1 Work to complete

5.2 Gate deliverable and decision

6. Gate 1 — Select / Pre-feasibility / FEL-2

6.1 Work to complete

6.2 Outside-view protocol — five LSE steps

6.3 Gate deliverable and decision

7. Gate 2 — Define / FEED / Feasibility / FEL-3

7.1 Engineering and scope

7.2 Estimating and schedule

7.3 Contracts, permits, HSE, ESG, financing

7.4 Mandatory pre-mortem before the file is sent

8. Gate 3 — The FID

8.1 Questions the committee must ask

8.2 Typical conditions precedent

9. Standard FID package (committee file)

9.1 Binder architecture

9.2 The decision note (three pages maximum)

9.3 What Finance must certify in tab 04

10. Investment appraisal — how the numbers must be built

10.1 Criterion hierarchy

10.2 Working formulae

10.3 LSE teaching mini-case

10.4 What a live FID adds to the course example

10.5 Ratio link (Module 7)

11. Risk, sensitivities and scenarios

11.1 Minimum set

11.2 Translating risk into governance

12. Cognitive biases and debiasing (LSE Module 8)

12.1 Biases that specifically hit the path to FID

12.2 Debiasing toolkit to write into the process

13. Governance, roles and RACI

13.1 Roles

13.2 Session rules

14. Master pre-FID checklists

14.1 Technical maturity and estimate

14.2 Economics and finance

14.3 Risk, legal, execution

15. After FID — what the brief must already specify

16. CV, interview and sponsor one-pager language

16.1 CV line

16.2 Interview answers

16.3 Sponsor one-liner in session

17. Annexes — glossary, formulae, sources

A. Working glossary

B. Formula reminders

C. Teaching sources used

D. Project instantiation

Close — what to remember